A breach of contract under the Sale of Goods Act, 1930, occurs when either the seller or the buyer fails to perform their obligations as per the terms of the contract. The Act provides specific remedies for the aggrieved party, aiming to place them in the position they would have been in had the contract been performed. These remedies are often read in conjunction with the general principles of contracts laid down in the Indian Contract Act, 1872, particularly concerning damages.
When the buyer is in default, the Sale of Goods Act empowers the seller with several remedies:
1. Suit for Price (Section 55):
Concept: This is a direct action by the seller to recover the agreed-upon price of the goods.
When available:
Distinction: Unlike a suit for damages (which aims to compensate for loss), a suit for price seeks to enforce the payment obligation. If property has not passed and the price is not payable on a certain day, the seller typically sues for damages for non-acceptance, not the price.
2. Damages for Non-Acceptance (Section 56):
Concept: When the buyer wrongfully neglects or refuses to accept and pay for the goods, the seller can claim damages for the loss suffered.
Measure of Damages: As per Section 73 of the Indian Contract Act, the measure of damages is the estimated loss directly and naturally resulting from the buyer's breach. Generally, this is the difference between the contract price and the market price of the goods on the date of the breach. The seller has a duty to mitigate their losses by, for example, reselling the goods.
Landmark Case: While Hadley v. Baxendale (1854) is a foundational English case (Section 73 Contract Act draws from it), in the Indian context, the principles are robustly applied. The Supreme Court often reiterates that the party suffering the breach must prove actual loss, even when a sum for liquidated damages is specified.
Latest Insight (Illustrative, not a direct SOGA case but relevant for damages): M/s. J.G. Engineers Private Limited vs. M/s. Bharat Aluminium Company Limited (2021) SC (Though this case primarily dealt with arbitration and Section 34 of the Arbitration Act, it reinforces the principle that while liquidated damages clauses exist, the claimant still has to demonstrate actual loss for damages to be awarded, unless the amount is a genuine pre-estimate of loss and not a penalty.) This principle is directly relevant to how damages for non-acceptance are assessed.
3. Remedies of an Unpaid Seller (Sections 45-54):
4. Repudiation of Contract Before Due Date (Anticipatory Breach - Section 60):
If either party indicates, before the performance date, that they will not fulfill the contract, the other party has an option:
5. Interest and Special Damages (Section 61):
The seller can recover interest on the price from the date it became due, if agreed upon, or at a reasonable rate determined by the court.
When the seller is in default, the Sale of Goods Act provides the buyer with the following remedies:
1. Damages for Non-Delivery (Section 57):
Concept: If the seller wrongfully neglects or refuses to deliver the goods, the buyer can sue for damages.
Measure of Damages: Similar to non-acceptance, the measure is usually the difference between the contract price and the market price of the goods on the date when they ought to have been delivered. If no time was fixed, then on the date of refusal to deliver. The buyer also has a duty to mitigate their losses (e.g., by purchasing substitute goods).
Case Example (Reflecting general principles of damages): Kesoram Cotton Mills Ltd. v. Gangadhar (AIR 1961 SC 576)
2. Specific Performance (Section 58):
Concept: This is an equitable remedy where the court may order the seller to actually deliver the specific or ascertained goods, instead of just paying damages. This is a discretionary power of the court.
When available: This remedy is usually granted when monetary compensation (damages) would not be an adequate remedy. This often happens if the goods are:
Crucial Link: Section 58 is subject to the provisions of the Specific Relief Act, 1963, which governs specific performance of contracts in general.
3. Remedy for Breach of Warranty (Section 59):
Concept: A warranty is a stipulation collateral to the main purpose of the contract, a breach of which gives rise to a claim for damages but not a right to reject the goods and treat the contract as repudiated (unless the buyer elects to treat a breach of condition as a breach of warranty).
Buyer's Options:
Important: Even if the buyer uses the first option, they can still sue for further damages if they have suffered additional losses.
M/s. Ambrish Kumar Gupta v. Union of India, (2021) Del HC
(While specific facts need precise verification, cases involving supply of goods with defects often refer to Section 59, allowing the buyer to claim a reduction in payment or damages based on the diminished value due to the breach of warranty on quality or fitness). This case would typically revolve around situations where goods supplied were not as per specifications, and the buyer sought recourse under Section 59.
4. Suit for Recovery of Price Paid (Implied - Section 61 read with Contract Act):
If the buyer has paid the price but the seller fails to deliver the goods, or there's a total failure of consideration, the buyer can sue for the recovery of the money paid. This is often an implied right under the Sale of Goods Act, reinforced by the principles of the Indian Contract Act (e.g., Section 65 for restitution).
5. Repudiation of Contract Before Due Date (Anticipatory Breach - Section 60):
As explained for the seller, the buyer also has the same options: treat the contract as terminated immediately and sue for damages, or wait for the performance date.
6. Interest and Special Damages (Section 61):